Delay analysis and claim files built on evidence. Alètheia reconstructs the real course of the project and measures the delays, with their causes.

Let’s talk about your record

The problem

  1. The facts exist, buried in thousands of letters, minutes and schedules.

  2. When the claim lands, everyone rebuilds the story from memory.

  3. And the best-documented account wins, not necessarily the true one.

The model

The method is chosen and fixed before looking at the result. It is the only way a delay analysis survives challenge.

  • methodnamed before the analysis, not picked afterwards
  • datathe dated schedule and the items received, nothing else
  • windowthe period over which delay is attributed
  • assumptionstated explicitly, including when it works against you
  • reproduciblesame data, same method, same result
  • adversarialmethod and sources are disclosed with the result

Methods

  • Queryable

    The evidence file answers a question asked in plain language

    « What items support the attribution in window 2? » The agent names the sources behind each conclusion. An analysis you can question is an analysis you can challenge: that is the point.

  • Windows

    The project is cut into periods, delay attributed period by period

    Time Slice Windows. You do not compare start and end and hope the gap explains itself: you look at where the slippage happens.

  • Planned / built

    The contract schedule set against what actually happened

    As-Planned versus As-Built. The most readable method in a meeting, the most fragile when data is missing: it then says so.

  • Collapse

    An event is removed to measure what it cost

    Collapsed As-Built. Without the weather, without the late instruction: what delay was left?

  • Concurrency

    Delays running at the same time are identified

    Two simultaneous causes do not add up. Concurrency candidates are exposed, not silently arbitrated.

  • Reconstruction

    The schedule as it stood on the date

    Not as remembered, nor as corrected since. It is the basis of any contemporaneous analysis.

  • The window 2 slippage stems from the wait for the package 3 shop drawingsSite meeting minutes no. 2214 March · received 15 March“the package 3 shop drawings have not been received to date”, notified on 21 MarchSite instruction no. 721 March · received 21 March“works on package 3 suspended pending the drawings” and lifted on 9 AprilDesign team letter ref. 2026-0419 April · received 10 April“issue of the shop drawings, revision C”.

    3 items cited · no statement without its source

    Traceability

    Every conclusion points to its evidence

    A statement without its document is not a conclusion, it is an opinion. The report tells them apart.

Against current practice

Current practiceWith the engine
Checking a conclusionask the analyst againask, and get the sources
Choice of methodafter seeing the resultfixed before the analysis
Schedule statefrom memory, or the latest filereconstructed at the chosen date
Concurrent delayssettled on expert say-socandidates identified and exposed
Reproducibilitydepends on the analystsame data, same result
Sourcescited when foundevery conclusion points to its item
Adversarialthe other side sees only the conclusionmethod and data disclosed with it

Accepted inputs

MS ProjectPrimavera P6minutescorrespondencesite recordsdated photos

What the engine does not do

It does not state the law. Establishing a fact is not qualifying it. Attributing liability and interpreting the contract are a lawyer’s work; the engine produces the material, not the legal conclusion.

It does not conclude without data. If a period’s records are missing, it says so and stops there. An analysis that fills gaps is not defensible.

It does not replace the expert. It does the long, reproducible work. Judgement on what the facts mean stays human, and signed.